我校太阳成集团的官方网站卢辉老师在T2级别期刊——《ENG CONSTR ARCHIT MA》上发表题为“Sharp schedule compression in urgent emergency construction projects via activity crashing, substitution and overlapping: a case study of Huoshengshan and Leishenshan Hospital projects in Wuhan ”。论文第一作者卢辉为太阳成集团的官方网站特任副教授。
Abstract / 摘要:
Purpose To meet the rapidly increasing demand for medical treatment during the outbreak of COVID-19, Huoshengshan and Leishenshan Hospital are rapidly built (9-12 days) in Wuhan. These two urgent emergency projects are unprecedented. In general, substantial literature suggests that the possibility of shortening a schedule by more than a quarter of its original duration is implausible. By contrast, the two projects had successfully compressed the schedules from months and years to about ten days. This study aims to investigate how this was done and provide references for future projects. Design/methodology/approach The study uses qualitative case study techniques to analyze the project practices in two urgent emergency projects. Data were gathered through semi-structured interviews and archival research. During interviews, interviewees were asked to describe the project practices adopted to overcome the challenges and freely share their experiences and knowledge. Findings The results illustrate that a high degree of schedule compression is achievable through tactful crashing, substitution and overlapping applications. The successful practices heavily rely on the high capacity of participants and necessary organization, management and technology innovations, such as three-level matrix organizational structure, reverse design method, site partition, mock-up room first strategies and prefabricated construction technology. For instance, the reverse design method is one of the most significant innovations to project simplification and accelerate and worthy of promotion for future emergency projects. Practical implications The empirical findings are significant as they evoke new thinking and direction for addressing the main challenges of sharp schedule compression and provide valuable references for future emergency projects, including selecting high-capacity contractors and replacing the conventional design methods with reverse design. Originality/value Substantial studies indicate that the maximum degree of schedule compression is highly unlikely to exceed 25%, but this study suggests that sharp compression is possible. Although with flaws in its beauty (i.e. compressing schedule at the expense of construction cost and quality), it is also a breakthrough. It provides the building block for future research in this fertile and unexplored area.
论文信息;
Title/题目:
Sharp schedule compression in urgent emergency construction projects via activity crashing, substitution and overlapping: a case study of Huoshengshan and Leishenshan Hospital projects in Wuhan
Authors/作者:
Lu, H (Lu, Hui) ; Wang, HW (Wang, Hongwei) ; Yu, DH (Yu, Dihua) ; Ye, J (Ye, Jian)
Keywords /关键词
COVID-19U;rgent emergency projects;Schedule compression;Crashing;Substitution;Overlapping
DOI: 10.1108/ECAM-07-2021-0654
全文链接:https://www.emerald.com/insight/content/doi/10.1108/ECAM-07-2021-0654/full/html